Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Consider the following timeline using three processors.


◦ This timeline is an illegal schedule because task F was started before task E was completed.
◦ This timeline is an illegal schedule because task E was started before task C was completed.
◦ This timeline is not an optimal schedule because the project can be scheduled with a finishing time of 11 hours.
◦ This timeline is an optimal schedule for three processors.
◦ none of these


Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question

Loise Hard

  • Sr. Member
  • ****
  • Posts: 340
This timeline is an illegal schedule because task F was started before task E was completed.



sjones

  • Hero Member
  • *****
  • Posts: 520
Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Consider the following timeline using three processors.


◦ This timeline is not optimal because task F was started after processor 3 was idle for 2 hours.
◦ This timeline is not an optimal schedule because the project can be scheduled with a finishing time of 12 hours.
◦ This timeline is an illegal schedule because task E was started before task C was completed.
◦ This timeline is an optimal schedule for three processors.
◦ none of these



jomama

  • Sr. Member
  • ****
  • Posts: 346
This timeline is an optimal schedule for three processors.



jhjkgdfhk

  • Hero Member
  • *****
  • Posts: 569
Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Consider the following timeline using two processors.


◦ This timeline is an optimal schedule.
◦ This is the timeline one gets using the decreasing-time algorithm.
◦ This is the timeline one gets using the critical-path algorithm.
◦ This timeline is an illegal schedule.
◦ none of these



djpooyouma

  • Sr. Member
  • ****
  • Posts: 325
This is the timeline one gets using the decreasing-time algorithm.



mydiamond

  • Hero Member
  • *****
  • Posts: 804
Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Consider the following timeline using two processors.


◦ This timeline is an illegal schedule.
◦ This timeline is an optimal schedule.
◦ This is the timeline one gets using the decreasing-time algorithm.
◦ This is the timeline one gets using the critical-path algorithm.
◦ none of these



Joy Chen

  • Sr. Member
  • ****
  • Posts: 354
This timeline is an illegal schedule.



bio_gurl

  • Hero Member
  • *****
  • Posts: 524
Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Consider the following timeline using two processors.


◦ This timeline is an optimal schedule.
◦ This timeline is an illegal schedule.
◦ This is the timeline one gets using the decreasing-time algorithm.
◦ This is the timeline one gets using the critical-path algorithm.
◦ none of these



frre432

  • Sr. Member
  • ****
  • Posts: 347
This is the timeline one gets using the critical-path algorithm.



 

Did you know?

By definition, when a medication is administered intravenously, its bioavailability is 100%.

Did you know?

Most strokes are caused when blood clots move to a blood vessel in the brain and block blood flow to that area. Thrombolytic therapy can be used to dissolve the clot quickly. If given within 3 hours of the first stroke symptoms, this therapy can help limit stroke damage and disability.

Did you know?

All adverse reactions are commonly charted in red ink in the patient's record and usually are noted on the front of the chart. Failure to follow correct documentation procedures may result in malpractice lawsuits.

Did you know?

The U.S. Pharmacopeia Medication Errors Reporting Program states that approximately 50% of all medication errors involve insulin.

Did you know?

For about 100 years, scientists thought that peptic ulcers were caused by stress, spicy food, and alcohol. Later, researchers added stomach acid to the list of causes and began treating ulcers with antacids. Now it is known that peptic ulcers are predominantly caused by Helicobacter pylori, a spiral-shaped bacterium that normally exist in the stomach.

For a complete list of videos, visit our video library