Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Consider the following timeline using two processors.


◦ This timeline is an optimal schedule.
◦ This is the timeline one gets using the critical-path algorithm.
◦ This is the timeline one gets using the decreasing-time algorithm.
◦ This timeline is an illegal schedule.
◦ none of these


Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question

maya.nigrin17@yahoo.com

  • Sr. Member
  • ****
  • Posts: 324
This timeline is an optimal schedule.



stephzh

  • Hero Member
  • *****
  • Posts: 556
Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Consider the following timeline using two processors.


◦ This is the timeline one gets using the critical-path algorithm.
◦ This is the timeline one gets using the decreasing-time algorithm.
◦ This timeline is an illegal schedule.
◦ This timeline is an optimal schedule.
◦ none of these



lou

  • Sr. Member
  • ****
  • Posts: 286

D2AR0N

  • Hero Member
  • *****
  • Posts: 561
Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Consider the following timeline using two processors.


◦ This is the timeline one gets using the critical-path algorithm.
◦ This timeline is an optimal schedule.
◦ This timeline is an illegal schedule.
◦ This is the timeline one gets using the decreasing-time algorithm.
◦ none of these



canderson530

  • Sr. Member
  • ****
  • Posts: 317
This timeline is an illegal schedule.



Hungry!

  • Hero Member
  • *****
  • Posts: 1,071

Question 1

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




The length of the critical path from C is
◦ 15 hours.
◦ 20 hours.
◦ 7 hours.
◦ 12 hours.
◦ none of these

Question 2

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




The length of the critical path from B is
◦ 15 hours.
◦ 11 hours.
◦ 22 hours.
◦ 4 hours.
◦ none of these



jjorrostieta

  • Sr. Member
  • ****
  • Posts: 298

Chloeellawright

  • Hero Member
  • *****
  • Posts: 588

Question 1

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




The length of the critical path for the entire project is
◦ 18 hours.
◦ 37 hours.
◦ 15 hours.
◦ 30 hours.
◦ none of these

Question 2

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using critical-path algorithm to schedule this project with two processors results in a finishing time of
◦ 22 hours.
◦ 18 hours.
◦ 19 hours.
◦ 23 hours.
◦ none of these



Tabitha_2016

  • Sr. Member
  • ****
  • Posts: 344

 

Did you know?

Adolescents often feel clumsy during puberty because during this time of development, their hands and feet grow faster than their arms and legs do. The body is therefore out of proportion. One out of five adolescents actually experiences growing pains during this period.

Did you know?

Aspirin may benefit 11 different cancers, including those of the colon, pancreas, lungs, prostate, breasts, and leukemia.

Did you know?

To maintain good kidney function, you should drink at least 3 quarts of water daily. Water dilutes urine and helps prevent concentrations of salts and minerals that can lead to kidney stone formation. Chronic dehydration is a major contributor to the development of kidney stones.

Did you know?

If all the neurons in the human body were lined up, they would stretch more than 600 miles.

Did you know?

Ether was used widely for surgeries but became less popular because of its flammability and its tendency to cause vomiting. In England, it was quickly replaced by chloroform, but this agent caused many deaths and lost popularity.

For a complete list of videos, visit our video library