Author Question: Suppose you have the following project digraph. (The numbers in parentheses represent hours.)The ... (Read 1006 times)

Tazate

  • Hero Member
  • *****
  • Posts: 532
Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Consider the following timeline using two processors.


◦ This timeline is an optimal schedule.
◦ This is the timeline one gets using the critical-path algorithm.
◦ This is the timeline one gets using the decreasing-time algorithm.
◦ This timeline is an illegal schedule.
◦ none of these


Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question

maya.nigrin17@yahoo.com

  • Sr. Member
  • ****
  • Posts: 324
This timeline is an optimal schedule.



stephzh

  • Hero Member
  • *****
  • Posts: 556
Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Consider the following timeline using two processors.


◦ This is the timeline one gets using the critical-path algorithm.
◦ This is the timeline one gets using the decreasing-time algorithm.
◦ This timeline is an illegal schedule.
◦ This timeline is an optimal schedule.
◦ none of these



lou

  • Sr. Member
  • ****
  • Posts: 286

D2AR0N

  • Hero Member
  • *****
  • Posts: 561
Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Consider the following timeline using two processors.


◦ This is the timeline one gets using the critical-path algorithm.
◦ This timeline is an optimal schedule.
◦ This timeline is an illegal schedule.
◦ This is the timeline one gets using the decreasing-time algorithm.
◦ none of these



canderson530

  • Sr. Member
  • ****
  • Posts: 317
This timeline is an illegal schedule.



Hungry!

  • Hero Member
  • *****
  • Posts: 1,071

Question 1

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




The length of the critical path from C is
◦ 15 hours.
◦ 20 hours.
◦ 7 hours.
◦ 12 hours.
◦ none of these

Question 2

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




The length of the critical path from B is
◦ 15 hours.
◦ 11 hours.
◦ 22 hours.
◦ 4 hours.
◦ none of these



jjorrostieta

  • Sr. Member
  • ****
  • Posts: 298

Chloeellawright

  • Hero Member
  • *****
  • Posts: 588

Question 1

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




The length of the critical path for the entire project is
◦ 18 hours.
◦ 37 hours.
◦ 15 hours.
◦ 30 hours.
◦ none of these

Question 2

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using critical-path algorithm to schedule this project with two processors results in a finishing time of
◦ 22 hours.
◦ 18 hours.
◦ 19 hours.
◦ 23 hours.
◦ none of these



Tabitha_2016

  • Sr. Member
  • ****
  • Posts: 344

 

Did you know?

Though methadone is often used to treat dependency on other opioids, the drug itself can be abused. Crushing or snorting methadone can achieve the opiate "rush" desired by addicts. Improper use such as these can lead to a dangerous dependency on methadone. This drug now accounts for nearly one-third of opioid-related deaths.

Did you know?

The Romans did not use numerals to indicate fractions but instead used words to indicate parts of a whole.

Did you know?

Prostaglandins were first isolated from human semen in Sweden in the 1930s. They were so named because the researcher thought that they came from the prostate gland. In fact, prostaglandins exist and are synthesized in almost every cell of the body.

Did you know?

The people with the highest levels of LDL are Mexican American males and non-Hispanic black females.

Did you know?

Thyroid conditions may make getting pregnant impossible.

For a complete list of videos, visit our video library