Author Question: Suppose you have the following project digraph. (The numbers in parentheses represent hours.)The ... (Read 1213 times)

Tazate

  • Hero Member
  • *****
  • Posts: 532
Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Consider the following timeline using two processors.


◦ This timeline is an optimal schedule.
◦ This is the timeline one gets using the critical-path algorithm.
◦ This is the timeline one gets using the decreasing-time algorithm.
◦ This timeline is an illegal schedule.
◦ none of these


Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question

maya.nigrin17@yahoo.com

  • Sr. Member
  • ****
  • Posts: 324
This timeline is an optimal schedule.



stephzh

  • Hero Member
  • *****
  • Posts: 556
Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Consider the following timeline using two processors.


◦ This is the timeline one gets using the critical-path algorithm.
◦ This is the timeline one gets using the decreasing-time algorithm.
◦ This timeline is an illegal schedule.
◦ This timeline is an optimal schedule.
◦ none of these



lou

  • Sr. Member
  • ****
  • Posts: 286

D2AR0N

  • Hero Member
  • *****
  • Posts: 561
Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Consider the following timeline using two processors.


◦ This is the timeline one gets using the critical-path algorithm.
◦ This timeline is an optimal schedule.
◦ This timeline is an illegal schedule.
◦ This is the timeline one gets using the decreasing-time algorithm.
◦ none of these



canderson530

  • Sr. Member
  • ****
  • Posts: 317
This timeline is an illegal schedule.



Hungry!

  • Hero Member
  • *****
  • Posts: 1,071

Question 1

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




The length of the critical path from C is
◦ 15 hours.
◦ 20 hours.
◦ 7 hours.
◦ 12 hours.
◦ none of these

Question 2

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




The length of the critical path from B is
◦ 15 hours.
◦ 11 hours.
◦ 22 hours.
◦ 4 hours.
◦ none of these



jjorrostieta

  • Sr. Member
  • ****
  • Posts: 298

Chloeellawright

  • Hero Member
  • *****
  • Posts: 588

Question 1

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




The length of the critical path for the entire project is
◦ 18 hours.
◦ 37 hours.
◦ 15 hours.
◦ 30 hours.
◦ none of these

Question 2

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using critical-path algorithm to schedule this project with two processors results in a finishing time of
◦ 22 hours.
◦ 18 hours.
◦ 19 hours.
◦ 23 hours.
◦ none of these



Tabitha_2016

  • Sr. Member
  • ****
  • Posts: 344

 

Did you know?

Signs and symptoms that may signify an eye tumor include general blurred vision, bulging eye(s), double vision, a sensation of a foreign body in the eye(s), iris defects, limited ability to move the eyelid(s), limited ability to move the eye(s), pain or discomfort in or around the eyes or eyelids, red or pink eyes, white or cloud spots on the eye(s), colored spots on the eyelid(s), swelling around the eyes, swollen eyelid(s), and general vision loss.

Did you know?

Acute bronchitis is an inflammation of the breathing tubes (bronchi), which causes increased mucus production and other changes. It is usually caused by bacteria or viruses, can be serious in people who have pulmonary or cardiac diseases, and can lead to pneumonia.

Did you know?

Chronic marijuana use can damage the white blood cells and reduce the immune system's ability to respond to disease by as much as 40%. Without a strong immune system, the body is vulnerable to all kinds of degenerative and infectious diseases.

Did you know?

Before a vaccine is licensed in the USA, the Food and Drug Administration (FDA) reviews it for safety and effectiveness. The CDC then reviews all studies again, as well as the American Academy of Pediatrics and the American Academy of Family Physicians. Every lot of vaccine is tested before administration to the public, and the FDA regularly inspects vaccine manufacturers' facilities.

Did you know?

Certain topical medications such as clotrimazole and betamethasone are not approved for use in children younger than 12 years of age. They must be used very cautiously, as directed by a doctor, to treat any child. Children have a much greater response to topical steroid medications.

For a complete list of videos, visit our video library